Mistakes and FAQ

Kitchen Remodel Budget Template: Contingency, Allowances and Change Orders

Build a kitchen remodel budget that survives surprises: how much contingency to hold, how allowances and change orders work, and a line-by-line budget template.

Updated · 5 min read

Kitchen Remodel Budget Template: Contingency, Allowances and Change Orders

A kitchen remodel budget that holds up has three layers: the base contract price, a contingency reserve for surprises (many professionals suggest roughly 10 to 20 percent), and a separate allowance for living costs outside the contract. Most overruns happen not because the contractor misquoted, but because homeowners had no buffer, treated allowances as real prices or approved changes without tracking them. This guide shows how to structure each layer and gives you a template.

Layer 1: the base budget

Start with the sum of your signed contract plus items you buy yourself. Typical components include:

Line itemNotes
Design feesDesigner, architect or engineer, if used
Permits and inspectionsOften paid by the contractor and passed through
Demolition and disposalDumpster, haul-away, lead or asbestos handling if needed
Framing and structuralBeams, wall changes
PlumbingFixtures, supply and drain changes, gas lines
ElectricalCircuits, lighting, outlets, panel upgrades
HVAC and ventilationRange hood ducting, vents
Insulation and drywallIncludes patching and finishing
CabinetsBoxes, doors, hardware, delivery and installation
CountertopsMaterial, fabrication, installation, sink cutout
BacksplashTile, setting materials, labor
FlooringMaterial, subfloor prep, installation
AppliancesPurchase, delivery, installation and haul-away of old units
Lighting fixturesFixtures and bulbs
Paint and trimWalls, ceiling, trim and cabinets if painted
CleaningFinal construction cleanup

Ask the contractor to provide a bid in this level of detail so you can see where your money goes.

Layer 2: contingency

Contingency pays for the unknown: rot behind a sink, outdated wiring, uneven floors, hidden plumbing issues and unforeseen code requirements. It should not be used for upgrades. How much to hold depends on risk:

SituationIllustrative contingency
Newer home, like-for-like swap, no layout changeAround 10 percent
Typical remodel with some plumbing or electrical changesAround 15 percent
Older home, layout changes or structural workAround 20 percent or more

These are rules of thumb, not official standards. Use the contingency calculator to compute your number.

Illustrative example: a base budget of $40,000 with a 15 percent contingency means holding $6,000. If the project finishes without surprises, you keep it, or spend it on something you agreed to postpone.

Rules for using the contingency

  1. Spend it only on documented, necessary issues, and ask the contractor to show you the problem with photos.
  2. Require a written change order before additional work.
  3. Track the balance in a spreadsheet and review it weekly.
  4. If it is nearly gone while work remains, pause and reassess before approving more.

Layer 3: costs outside the contract

Many budgets omit costs that fall outside the contractor's price:

  • Temporary kitchen supplies and extra meals out.
  • Storage rental or movers if belongings must be moved.
  • Cleaning of the rest of the house after construction.
  • Window treatments, furniture, décor or small items you decide to add.
  • Higher utility bills during construction or from new appliances.
  • Homeowner's insurance adjustments.
  • Loan interest during construction if you draw funds gradually.

Set these aside separately and include them in the "total available" figure the calculator displays.

How allowances work

An allowance is a placeholder amount in the contract for an item not yet chosen, such as "$3,000 for countertops" or "$1,500 for lighting fixtures." If your final selection costs more than the allowance, you pay the difference; if less, you may receive a credit. Problems arise when the allowance is unrealistic. Check each allowance against actual prices for items you like, and ask your contractor whether the allowance includes installation, tax and delivery. A low allowance can make a bid look attractive but leads to overage later. See our guide on getting the best deal for how to compare bids with different allowances.

How change orders work

A change order is a written, signed amendment to the contract that adds, removes or alters work. A good change order states:

  • A description of the change and why it is needed.
  • The cost (add or credit) and any markup.
  • The effect on the schedule.
  • The new total contract price.
  • Signatures from both parties and a date.

Do not approve major changes verbally. Verbal agreements are hard to prove and invite disputes. Keep a running ledger of approved changes so you always know the current contract price.

A worked budget example

The numbers below are illustrative.

ItemAmount
Contract price (including permits and disposal)$34,000
Appliances purchased separately$6,500
Base budget$40,500
Contingency at 15 percent$6,075
Temporary kitchen and meals$1,800
Post-project items (window treatments, small décor)$1,000
Total available$49,375

If you are financing, borrow for the base plus contingency, and cover the living costs from cash flow if possible. Use the loan calculator to see what payments look like.

Managing the budget during construction

  • Weekly check-in: review progress against the payment schedule and the contingency balance.
  • Pay for progress: release payments after milestones are met, not before.
  • Document changes: collect signed change orders and keep invoices for items you buy.
  • Watch for scope creep: a "while we are at it" upgrade can add up quickly. Decide whether each one is essential or can wait.
  • Keep receipts and photographs: they help with warranty claims, insurance and your records for tax basis.

What if you go over budget?

If costs exceed the budget despite planning, consider these steps in order:

  1. Review whether the extra costs are truly necessary.
  2. Look for savings in finishes not yet purchased, such as fixtures, hardware or lighting.
  3. Ask whether the scope can be phased, deferring items such as backsplash or an island.
  4. Compare financing choices for the shortfall; see financing a kitchen remodel.
  5. Avoid cutting safety, structural or code-required work.

Frequently asked questions

Should the contractor know my contingency amount?

It is usually wise to keep your contingency private. Share the base budget and let the contractor price the scope.

Can I use the contingency for upgrades?

Better not to. Treat it as insurance against surprises. If you want upgrades, price them as change orders from your base budget or wait until the end.

What if I do not use the contingency?

Keep the savings, pay down any loan or use it for something you deferred.

How do I track expenses?

A simple spreadsheet with columns for item, budget, actual cost and notes works well. Update it each week.